Fields Park Construction Schedule

For Fields Park it’s more of what has been occurring. They will go as far as they can using the direct pipe installation method as opposed to the hydraulic hammering. The contractor is currently saying based on current progress, the earliest that they would switch to hammering would be the last week in March, although early April is more likely.

Week of March 4 - Direct Pipe installation with mining

Week of March 11 - Direct Pipe installation with mining, starting onshore vault installation on N Lewis Ave

Week of March 18 – Direct Pipe installation with mining, vault installation on N Lewis Ave

Week of March 25 – Direct pipe installation with mining, vault installation on N Lewis Ave and N Loring St